Q&R audit schedule — recurring assurance cadence
Owner: Quality & Risk (Quality & Risk Director). Layer: Operating doc (
reports/). What Q&R audits and when. Caveat: cadence automation is a no-op (AR-003; risk R-004) — until wired, every entry below is run manually at the relevant wave checkpoint; the PMO records the result intracker.md(master plan §11 R6 / §12). This is a stub seeded at Wave 3; it fills as cycles run.
Standing cadence
| Cadence | What | Procedure | Run mode (today) |
|---|---|---|---|
| Each wave checkpoint | Four-test stratified sample on the just-completed wave (anti-theater gate; R1/R11) | SOP-087 | manual (no shell → gates logic-traced + Operations/PMO machine-attest) |
| Each cycle | Control-gap follow-up — re-confirm every open row in the control-gap registry | SOP-085 + SOP-086 | manual |
| On any new High/Critical | Open/update the risk register row; notify Principal/affected Lead; recompute posture | SOP-086 | manual |
| Quarterly | Policy-conformance audit (“are we following our SOPs / HR policies”) | SOP-085 | manual (deferred until a cycle’s worth of practice exists to audit) |
Open commitments (carry-forward)
- Wave-1/2 control gaps — confirm closure at the next cycle (see the control-gap
registry in
reports/risk-register.md: G-W1-1, G-W1-2, G-W2-1…4). - R-001 (Slack ToS) — confirm the deletion cron stays disabled at each Wave-3 checkpoint until the migrations + fallback job ship.
- R-003 (fan-in blind spot) — re-assess when Operations lands a producer-presence CI complement.
See also: docs/units/quality-risk/charter.md · reports/risk-register.md ·
SOP-085 / SOP-086 / SOP-087 · master plan §11 / §12.