SOP-005 — Phase-gate quorum & decision rules
Standard Operating Procedure · owner: Operations (Process Engineer) with the COO (tie-break + cluster readiness) and the CPTO (strategic gate assessment). Layer: SOP/Runbook (
docs/canon.md). References:docs/methodology.md(the Standard Flow / five gates), ORG.md §COO Cluster, §CPTO Cluster.
Purpose
Make every phase-gate decision predictable, quorate, and time-boxed, so the
venture advances on evidence — not on whoever happens to be in the room — and
never stalls because a required sign-off is missing. This SOP defines, for each of
the five gates in docs/methodology.md (Ideate → Plan → Build → Grow →
Operate): who must sign off (quorum), the 48-hour decision SLA, what a
gate verdict is, and how the COO breaks a tie when sign-offs conflict or
the SLA lapses.
Scope
Applies to the four inter-phase gates the venture passes through —
Ideate→Plan, Plan→Build, Build→Grow, Grow→Operate — plus the
Operate→Ideate loop-back when needs evolve. The CPTO and Principal govern
gate methodology integrity (docs/methodology.md); this SOP governs the
operational mechanics of reaching a quorate, on-time verdict. It does not
change what the gate’s evidence bar is — only how the decision is taken.
Flow
flowchart LR
E["Evidence ready<br/>(Design Research<br/>+ deliverable)"] --> Q{"Quorum<br/>assembled?"}
Q -->|no| W["Wait /<br/>chase sign-off"]
W --> Q
Q -->|yes| R["Reviewers vote<br/>within 48h SLA"]
R --> D{"Unanimous<br/>advance?"}
D -->|yes| A["Advance<br/>(Principal confirms)"]
D -->|no / SLA lapsed| T["COO tie-break"]
T --> A
T --> H["Hold<br/>(named remediation)"]
A --> Rec["Record verdict in the<br/>day's report Decisions"]
H --> Rec
classDef s fill:#1d4ed8,color:#fff,stroke:#1e3a8a
classDef d fill:#0f766e,color:#fff,stroke:#134e4a
class E,W,R,A,T,H,Rec s
class Q,D d
Text fallback: Evidence ready (Design Research evidence + the phase
deliverable) → Quorum assembled? (if no, chase the missing sign-off and
re-check) → reviewers vote within the 48h SLA → unanimous advance? → if
yes, Advance (Principal confirms); if no or the SLA lapsed, COO tie-break
→ either Advance or Hold with named remediation → Record verdict in
the Decisions section of that day’s report (reports/<date>-report.md), and
open an ADR (docs/adr/) only when the gate decision is architecturally
load-bearing.
Quorum by gate
Quorum = the set of sign-offs that must be present for a verdict to be valid.
Leads are taken from docs/methodology.md §Phases and ORG.md. The Principal
confirms every advance; the CPTO owns the strategic gate assessment at every
gate; the COO confirms operational/quality readiness where a COO-cluster
Director is on the gate.
| Gate | Required sign-offs (quorum) | COO-cluster readiness input |
|---|---|---|
| Ideate → Plan | CPTO · Design Research Director · Documentarian · Principal (confirms) | Project Manager confirms the concept is sequenceable (Delivery/PMO) |
| Plan → Build | CPTO · Project Manager · Documentarian · Principal (confirms) | COO confirms the plan is sequenced with milestones and capacity is not overcommitted (in writing, before the gate closes) |
| Build → Grow | CPTO · Quality & Risk Director · Security Director · Principal (confirms) | COO confirms Q&R has cleared the build to its rubric and the Security Director has reviewed the surface change |
| Grow → Operate | CPTO · Growth Director · Quality & Risk Director · Principal (confirms) | COO confirms the operating cadence + runbooks exist for sustainable run |
| Operate → Ideate (loop-back) | CPTO · Principal (confirms) | COO confirms no open Critical from the operate cycle blocks the next loop |
Notes:
- The Design Research Director supplies the evidence at every gate
(
docs/methodology.md); evidence absence is itself a Hold condition, not a vote. - A sign-off is valid only against committed evidence — a reviewer voting without reading the deliverable does not count toward quorum.
- Formal gate reviews may use External Review Partners (360°) and
/agents:review; their report is input to the reviewers, not a quorum vote.
The 48-hour SLA
Once evidence is ready and the gate is opened (quorum reviewers notified, via the Personal Assistant where the Principal is a reviewer), each required reviewer must return a verdict within 48 hours.
- The 48h clock starts when the last required reviewer is notified with the committed evidence in hand — not when the deliverable was first drafted.
- A reviewer who needs more time must say so within the 48h and name a new return time; silence past 48h is not an implicit approval — it triggers the COO tie-break path below.
- This SLA is the same one ratified in the 2026-05-31 C-suite audit for the Ideate gate; this SOP generalises it to all five gates.
Verdicts
A reviewer returns exactly one of:
| Verdict | Meaning |
|---|---|
| Advance | Evidence meets the gate bar; proceed to the next phase. |
| Hold | Bar not met; advance is blocked until named remediation is done. A bare “no” is not a verdict — the reviewer states what must change. |
| Advance-with-conditions | Proceed, but listed conditions must close on a named date in the next phase. Counts as Advance for quorum; conditions are tracked by the Project Manager. |
The gate advances only when all quorum reviewers return Advance or Advance-with-conditions and the Principal confirms. Any Hold blocks the advance until resolved or escalated.
COO tie-break
The COO breaks ties; the COO does not override the evidence bar.
- Trigger. The COO holds the deciding call when either: (a) quorum reviewers split between Advance and Hold, or (b) a required reviewer misses the 48h SLA without claiming an extension.
- Read both positions from source (per the COO charter, Process B) — the deliverable, the Design Research evidence, and each reviewer’s stated rationale. Reconstructing from memory is not allowed.
- Apply the governing constraint first. A Critical Security or Quality & Risk Hold is not breakable to Advance — these are second-line controls; the COO’s only move is Hold + named remediation + a deadline, or escalate to the Principal for the deciding call. The COO may break ties toward Hold freely; breaking toward Advance is permitted only when no Critical control finding is open.
- Issue a binding call. State the decision, the governing rationale, what each party does next, and any condition under which it is revisited. Ambiguous rulings are not rulings (COO charter, Process B.4).
- SLA-lapse default. If a non-Critical reviewer simply missed the SLA, the COO may proceed on the remaining quorum after one explicit chase; the lapse and the chase are recorded. A missed sign-off from Q&R or Security is never defaulted past — it escalates.
- Record the tie-break in the Decisions section of that day’s report
(
reports/<date>-report.md) — and as an ADR (docs/adr/) if it is architecturally load-bearing — then reflect it in the next cluster status brief (reports/<date>-coo-cluster-status.md).
Boundaries
- The CPTO and Principal own gate methodology integrity and the strategic assessment; this SOP owns the decision mechanics only.
- The COO confirms operational/quality readiness and breaks ties — the COO does not author the gate evidence, the project plan, the audit, or the threat model (COO charter, Guardrails). Those remain with the named Directors.
- Spend implications surface to the Finance Director; rule gaps surface to Golden Rule (GR-3) — neither is decided at the gate.
Definition of Done (DoD)
A gate verdict is done only when:
- [ ] Quorum for that gate (table above) returned a verdict against committed evidence within the 48h SLA, or the COO tie-break path was followed.
- [ ] The Principal confirmed any advance.
- [ ] The verdict (Advance / Hold / Advance-with-conditions) is recorded in the
Decisions section of that day’s report (
reports/<date>-report.md) with date, parties, decision, rationale, and follow-ups — promoted to an ADR (docs/adr/) only when the gate decision is architecturally load-bearing. - [ ] Any Advance-with-conditions items are logged with the Project Manager and a named close date.
- [ ] The outcome is reflected in the next COO cluster status brief and handed to the Archivist.
- [ ] Any Mermaid diagram validated (mermaid MCP) and carries a text fallback (per SOP-002).